To help keep our citizens informed about the Pipeline Road construction we will post updated information here. 

View the original Notice of Construction

January 24, 2018 Contractor is working on underground utilities on the north side of Pipeline Road.  Should be finished by the end of this week.  AT&T is also working on north side in preparation of removing their lines off the poles. Next week removal of pavement for ATMOS transmission line.
February 8, 2018 Contractor is excavating area on the north side of roadway for Atmos transmission work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove poles.  These poles must be removed prior to Atmos starting transmission relocation. Atmos transmission work expected to start the week of February 26th.
 February 14, 2018

Contractor is excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Atmos transmission work expected to start the week of February 26th.

 February 22, 2018 Next week, weather permitting, contractor will finish excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T will continue to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Due to weather delays Atmos transmission work is expected to start the week of March 12th.  Once started the gas transmission work should last approximately 90 days.

 March 2, 2018

AT&T will continue to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Due to weather delays Atmos transmission work is expected to start the week of March 12th.  Once started the gas transmission work should last approximately 90 days.

 March 8, 2018

AT&T has removed lines from poles on north side of Pipeline.  They need to remove 4 wooden poles which should be done this week.  Oncor can now remove the rest of the north side poles that are in conflict.

Atmos transmission work is expected to start the week of March 12th.  Gas transmission work should last approximately 90 days.

 March 14, 2018

All poles that were in conflict have been removed from the north side of the roadway.

Atmos transmission work has been rescheduled to start on March 26, 2018 due to the gas main situation in Dallas. 

No other work can be accomplished until the gas transmission line has been relocated.

 March 21, 2018

Atmos transmission work is scheduled to begin on March 26, 2018.

 March 29, 2018

Due to the rain the Atmos transmission work has been delayed.  It is now scheduled to start on April 2, 2018.  They will begin on the east side of the project close to the Mary Drive intersection.  The transmission line construction is estimated to take 90 days.

 April 5, 2018 Atmos sub-contractor has been onsite locating existing utilities and surveying for directional bore.  Should start directional boring operation Monday or Tuesday of next week.
 April 12, 2018 Atmos sub-contractor is onsite working on new transmission line.