Pipeline Road Project

Print
Press Enter to show all options, press Tab go to next option

To help keep our citizens informed about the Pipeline Road construction we will post updated information here. 

View the original Notice of Construction

January 24, 2018 Contractor is working on underground utilities on the north side of Pipeline Road.  Should be finished by the end of this week.  AT&T is also working on north side in preparation of removing their lines off the poles. Next week removal of pavement for ATMOS transmission line.
February 8, 2018 Contractor is excavating area on the north side of roadway for Atmos transmission work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove poles.  These poles must be removed prior to Atmos starting transmission relocation. Atmos transmission work expected to start the week of February 26th.
 February 14, 2018

Contractor is excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Atmos transmission work expected to start the week of February 26th.

 February 22, 2018 Next week, weather permitting, contractor will finish excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T will continue to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Due to weather delays Atmos transmission work is expected to start the week of March 12th.  Once started the gas transmission work should last approximately 90 days.

 March 2, 2018

AT&T will continue to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Due to weather delays Atmos transmission work is expected to start the week of March 12th.  Once started the gas transmission work should last approximately 90 days.

 March 8, 2018

AT&T has removed lines from poles on north side of Pipeline.  They need to remove 4 wooden poles which should be done this week.  Oncor can now remove the rest of the north side poles that are in conflict.

Atmos transmission work is expected to start the week of March 12th.  Gas transmission work should last approximately 90 days.

 March 14, 2018

All poles that were in conflict have been removed from the north side of the roadway.

Atmos transmission work has been rescheduled to start on March 26, 2018 due to the gas main situation in Dallas. 

No other work can be accomplished until the gas transmission line has been relocated.

 March 21, 2018

Atmos transmission work is scheduled to begin on March 26, 2018.

 March 29, 2018

Due to the rain the Atmos transmission work has been delayed.  It is now scheduled to start on April 2, 2018.  They will begin on the east side of the project close to the Mary Drive intersection.  The transmission line construction is estimated to take 90 days.

 April 5, 2018 Atmos sub-contractor has been onsite locating existing utilities and surveying for directional bore.  Should start directional boring operation Monday or Tuesday of next week.
 April 12, 2018 Atmos sub-contractor is onsite working on new transmission line.
 April 25, 2018 Atmos sub-contractor is onsite working on new transmission line.  Trailwood Drive at Pipeline Road is scheduled to be closed on Friday April 27th for approximately 1 week. Detour routes will be marked.  Contractor is planning on working Saturday and Sunday to complete bore east to Mary.
 May 3, 2018

Atmos sub-contractor is onsite working on new transmission line. Trailwood Drive intersection at Pipeline Road is open.

 May 10, 2018

Atmos sub-contractor is onsite working on new transmission line.  Will possibly start bore under Precinct Line Road latter part of next week.  McClendon Construction is removing pavement east of Hurstview Drive.

 May 17, 2018

McClendon Construction is removing pavement east of Hurstview Drive and will continue to work on grading.  Atmos gas transmission work will continue working west of Hurstview.  Any intersection closures will be coordinated with the City and advance notification will be given.  Gas line bore at Precinct Line Road has been delayed due to utility conflict. 

 May 24, 2018 Atmos sub-contractor is onsite working on new transmission line.  Will start boring process on west side of project Tuesday May 29th.  Trailwood Drive at Pipeline Road is scheduled to be closed on Wednesday May 30th for 1 day. Detour routes will be marked.  McClendon will be doing dirt work east of Hurstview in preparation of lime stabilization of sub-grade.
 May 30, 2018

Atmos sub-contractor is onsite working on new transmission line.    Trailwood Drive at Pipeline Road is scheduled to be closed on Saturday June 2nd for 1 day and Forest Oaks is scheduled to be closed Sunday June 3rd for 1 day. Detour routes will be marked.  McClendon will be working on stabilizing the subgrade from Hurstview to Barbara Ann.  The intersection of Hurstview north of Pipeline Road will be closed from June 4 till June 7th and will reopen Friday June 8th.  Detour routes will be marked.

 June 6, 2018 Atmos sub-contractor is onsite working on boring new transmission line under Precinct Line Road. McClendon will be working on stabilizing the subgrade from Hurstview to Barbara Ann. The intersection of Hurstview north of Pipeline Road will be closed from June 11 till June 14th and will reopen Friday June 15th. Detour routes will be marked
 June 20, 2018

Atmos sub-contractor will continue working on transmission line.  Walmart drive is scheduled to be closed Thursday June 21st after 8PM and will reopen by Friday morning.  Walmart has been notified.  McClendon will be working on recutting the stabilized subgrade from Hurstview to Barbara Ann and recutting the subgrade from Hurstview west to Trailwood.