Pipeline Road Project

Print
Press Enter to show all options, press Tab go to next option

To help keep our citizens informed about the Pipeline Road construction we will post updated information here. 

View the original Notice of Construction

January 24, 2018 Contractor is working on underground utilities on the north side of Pipeline Road.  Should be finished by the end of this week.  AT&T is also working on north side in preparation of removing their lines off the poles. Next week removal of pavement for ATMOS transmission line.
February 8, 2018 Contractor is excavating area on the north side of roadway for Atmos transmission work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove poles.  These poles must be removed prior to Atmos starting transmission relocation. Atmos transmission work expected to start the week of February 26th.
 February 14, 2018

Contractor is excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T is continuing to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

Atmos transmission work expected to start the week of February 26th.

 February 22, 2018 Next week, weather permitting, contractor will finish excavating area on the north side of roadway in preparation of Atmos transmission line work.  AT&T will continue to work toward removal of lines on poles on north side of roadway so Oncor can remove the north side wooden poles.  These poles must be removed prior to Atmos starting transmission relocation.

 

Due to weather delays Atmos transmission work is expected to start the week of March 12th.  Once started the gas transmission work should last approximately 90 days.